This is an old revision of the document!
The date indicates when the tasks should be completed by. The symbols mean the following:
⊗ Not complete
— Significant work has been done on this task
✔ Complete
✔ The physical load cell connection must be made
✔ A sequence of commands must be made through programming in order to do initial testing
✔ The design of the control tower must be made with specific measurements
- Control tower must be built
- Initial accuracy data must be collected from multiple tests in the CNC machine
✔ Data should be compiled in excel or matlab for analyzation